PRINCE2 2009 - Plans part 26

The PRINCE2® approach

Prepare the schedule

Calculate total resource requirements and costs

The resource requirements can be tabulated, and the cost of the resources and other costs calculated to produce the plan’s budget.


The budget should include:

  • Costs of the activities to develop and verify the specialist products, and the cost of the project management activities
  • Risk budget (see the section covering ‘Risk’)
  • Change budget (see the section covering ‘Change’)
  • Cost tolerances.

The use of risk budgets and change budgets is optional.