The PRINCE2® approach

Delegating authority

Project Board controls

The main controls available to the Project Board include:

Authorizations

The Project Board uses the Directing a Project process to authorize initiation, authorize the project, authorize each stage and, finally, authorize project closure:

  • After the pre-project process Starting up a Project, the Project Board authorizes progress to the initiation stage, which is the official ‘start’ of the project
  • After the Initiating a Project process, the Project Board reviews the information from the Project Initiation Documentation and, if satisfied that there is sufficient reason to go ahead with the project, can approve the Project Initiation Documentation and authorize the project itself
  • After the Managing a Stage Boundary process, the Project Board reviews a Stage Plan or Exception Plan, and can either approve the plan, with its relevant tolerances for the next management stage, or, if there is insufficient justification to continue with the project, trigger premature closure of the project
  • After the Closing a Project process, the Project Board reviews the End Project Report and, if satisfied that the project is complete or has nothing more to offer, can authorize its closure
Progress updates

Including Highlight Reports and End Stage Reports

Exceptions and changes

Including Exception Reports and Issue Reports.

When the Project Board has agreed stage tolerances with the Project Manager, it is kept informed of progress by means of Highlight Reports.
There is no need for regular progress meetings during this stage, although personnel with Project Assurance responsibilities will require regular contact with the Project Manager and team members.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.