Prince2 header
products page

PRINCE2 2009 - Progress part 10

The PRINCE2 approach

Use of management stages for control

Number of stages

The use of management stages in a PRINCE2® project is mandatory, but the number of stages is flexible and depends on the scale and risk of the project.
Every PRINCE2 project consists of at least two management stages.
The initiation stage is mandatory as it ensures that there is a firm basis for the project, which is understood by all parties.
There should also be at least one other management stage to cover the remainder of the project.
For larger projects, additional management stages may be needed to enable the project management team to have an optimal level of planning and control.

Defining management stages is fundamentally a process of balancing:

  • How far ahead in the project it is sensible to plan
  • Where the key decision points need to be on the project
  • The amount of risk within a project
  • Too many short management stages (increasing the project management overhead) versus too few lengthy ones (reducing the level of control)
  • How confident the Project Board and Project Manager are in proceeding

The number of management stages required will be dictated by the nature of the project and its duration.
For short-duration projects (where the project can be completed within the planning horizon, for example), the introduction of multiple management stages could result in unnecessary ‘overheads’ and additional costs.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.