Introduction
Topics
Detailed planning
This will be part of a risk management process.
This process is covered in much more detail in the 'The Complete Risk Management package'
It is also covered as part of the PRINCE2® methodology under the component 'Management of Risk'.
All possible risks to the smooth running of the project should be identified.
This should be done at all levels of the project.
Naturally, committees like the Project Board will identify risks at a higher level, such as,
the change in future exchange rates or interest rates.
In addition, managers at all levels must identify potential issue within their own remits, for example, a supplier going bust, changes in regulatory issues,
delays in the delivery of critical equipment.
For each risk the impact on the project must be assessed.
This will be a mixture of the likelihood of the risk occurring and the level of the affect (that is the impact) on the project.
We know that if a risk will have a dramatic affect, for example and earthquake, it may be very unlikely to occur and as such could be ignored.
On the other hand it may be very likely to occur, for example exchange rate movement, but may be assessed as having only a minor affect.
The project management team may only be interested in high likelihood / high affect risks.
For these the project management team must make sure that suitable contingency plans are in place.
These must be costed and allowed for in the budget.
All risks raised must be recorded along with any actions decided.
Those responsible for implementing actions should be identified and recorded.
The progress of any existing risk issues must be addressed at suitable review points.
If you use any particular methods for assessing the risks or any assumptions etc these should also be recorded.
Risks are recorded within PRINCE2 2005 using the Risk Log and within PRINCE2 2009 [see ‘The Complete Project Management plus PRINCE2’] as the Risk Register.
Templates are provided in the product package.
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
59The components [see The components]
Analysing Risks [see Planning (PL) - part 7]
Designing a Project Management Team [see Starting up a Project (SU) - part 3]
Management of Risk [see Management of Risk - part 1]
Organization [see Organization - part 1]
Plans - benefits [see Plans - part 1]
Project Board [see Organization - part 2]
Risk [see Management of Risk - part 1]
Risk Log [see Managing Stage Boundaries (SB) - part 5]
Updating the Risk Log [see Managing Stage Boundaries (SB) - part 5]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Dealing with changes to the project management team [see Organization - The PRINCE2 approach - The project management team – Dealing with changes to the project management team]
Organization [see Organization - Purpose]
Project Board [see Organization - The PRINCE2 approach - The project management team - Project Board]
Project management team structure [see Organization - The PRINCE2 approach - The project management team]
Size of the Project Board [see Organization - The PRINCE2 approach - The project management team - Size of the Project Board]
Plans
Activities [see Plans - The PRINCE2 approach - Identify activities and dependencies - Activities]
Analyse the risks [see Plans - The PRINCE2 approach - Analyse the risks]
Create the product breakdown structure [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Create the product breakdown structure]
Create the product flow diagram [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Create the product flow diagram]
Dependencies [see Plans - The PRINCE2 approach - Identify activities and dependencies - Dependencies]
Design the plan - Write the Project Product Description [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Write the Project Product Description]
Document the plan [see Plans - The PRINCE2 approach - Document the plan]
Exception Plans [see Plans - Plans defined - Exception Plans]
Levels of plan [see Plans - Plans defined - Levels of plan]
Plans - Define and analyse the products [see Plans - The PRINCE2 approach - Define and analyse the products]
Plans - Philosophy [see Plans - The PRINCE2 approach - Philosophy]
Plans - Purpose [see Plans - Purpose]
Prepare estimates [see Plans - The PRINCE2 approach - Prepare estimates]
Prepare the schedule - Agree control points [see Plans - The PRINCE2 approach - Prepare the schedule - Agree control points]
Prepare the schedule - Assess resource availability [see Plans - The PRINCE2 approach - Prepare the schedule - Assess resource availability]
Prepare the schedule - Assign resources [see Plans - The PRINCE2 approach - Prepare the schedule - Assign resources]
Prepare the schedule - Calculate total resource requirements and costs [see Plans - The PRINCE2 approach - Prepare the schedule - Calculate total resource requirements and costs]
Prepare the schedule - Define activity sequence [see Plans - The PRINCE2 approach - Prepare the schedule - Define activity sequence]
Prepare the schedule - Define milestones [see Plans - The PRINCE2 approach - Prepare the schedule - Define milestones]
Prepare the schedule - Level resource usage [see Plans - The PRINCE2 approach - Prepare the schedule - Level resource usage]
Prepare the schedule [see Plans - The PRINCE2 approach - Prepare the schedule]
Prerequisites for planning – design the plan [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan]
Project Plan [see Plans - Plans defined - The Project Plan]
Stage Plans [see Plans - Plans defined - Stage Plans]
Team Plans [see Plans - Plans defined - Team Plans]
What is a plan? [see Plans - Plans defined - What is a plan?]
What is planning? [see Plans - Plans defined - What is planning?]
Write the Product Descriptions [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Write the Product Descriptions]
Risk
Assess [see Risk - Risk management procedure - Assess]
Communicate [see Risk - Risk management procedure - Communicate]
Identify – part 1 [see Risk - Risk management procedure - Identify – part 1]
Implement [see Risk - Risk management procedure - Implement]
Plan [see Risk - Risk management procedure - Plan]
Risk management in projects [see Risk - Risk management in projects]
Risk management procedure [see Risk - Risk management procedure]
Risk Management Strategy [see Risk - Risk Management Strategy]
Risk Register [see Risk - Risk Register]
What is a risk? [see Risk - Risk defined - What is a risk?]
What is at risk? [see Risk - Risk defined - What is at risk?]
What is risk management? [see Risk - Risk defined - What is risk management?]
Change
Capture [see Change - The PRINCE2 approach - Issue and change control procedure - Capture]
Configuration Item Records [see Change - The PRINCE2 approach - Establish controls - Configuration Item Records]
Configuration management [see Change - Change defined - Configuration management]
Configuration management procedure [see Change - The PRINCE2 approach - Configuration management procedure]
Configuration Management Strategy [see Change - The PRINCE2 approach - Establish controls - Configuration Management Strategy]
Daily Log [see Change - The PRINCE2 approach - Establish controls - Daily Log]
Decide [see Change - The PRINCE2 approach - Issue and change control procedure - Decide]
Establish controls [see Change - The PRINCE2 approach - Establish controls]
Examine [see Change - The PRINCE2 approach - Issue and change control procedure - Examine]
Implement [see Change - The PRINCE2 approach - Issue and change control procedure - Implement]
Issue and change control [see Change - Change defined - Issue and change control]
Issue and change control procedure [see Change - The PRINCE2 approach - Issue and change control procedure]
Issue Register [see Change - The PRINCE2 approach - Establish controls - Issue Register]
Issue Report [see Change - The PRINCE2 approach - Establish controls - Issue Report]
Issues [see Change - Change defined - Issues]
Product Status Account [see Change - The PRINCE2 approach - Establish controls - Product Status Account]
Propose [see Change - The PRINCE2 approach - Issue and change control procedure - Propose]
Types of issue [see Change - Change defined - Types of issue]
Process
Final delivery stage [see Introduction to processes - The PRINCE2 journey - Final delivery stage]
Initiation stage [see Introduction to processes - The PRINCE2 journey - Initiation stage]
Pre-project [see Introduction to processes - The PRINCE2 journey - Pre-project]
Subsequent delivery stages [see Introduction to processes - The PRINCE2 journey - Subsequent delivery stages]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Introduction
What is risk? [see What is risk?]
6 questions to define the project [see 6 questions to define the project]
The key areas of concern [see The key areas of concern]
What should risk analysis provide? [see What should risk analysis provide?]
3 Ways to view risk management [see 3 Ways to view risk management]
General comments on risk assessment [see General comments on risk assessment]
Accountability [see Accountability]
General comments on planning [see General comments on planning]
What are the core process steps to assess a risk? [see What are the core process steps to assess a risk?]
Simple process outline [see Simple process outline]
What are the basic overall process steps? [see What are the basic overall process steps?]
Stakeholders [see Stakeholders]
Success measures [see Success measures]
Why carry out Risk Assessment? [see Why carry out Risk Assessment?]
The Risk Management Process
The Risk Management Process [see The Risk Management Process]
The Risk Management Process - define the project [see The RMP define the project]
The Risk Management Process - define the project management process [see The RMP define the project management process]
The Risk Management Process - identify the risks and responses [see The RMP identify the risks and responses]
The Risk Management Process - organise - prioritise risks and responses [see The RMP organise - prioritise risks and responses]
The Risk Management Process - ownership risks responsibilities and contractors [see The RMP ownership risks responsibilities and contractors]
The Risk Management Process - estimate - size the risks [see The RMP estimate - size the risks]
The Risk Management Process - Estimate
The Risk Management Process - estimate - size the risks [see The RMP estimate - size the risks]
Simple estimating of risk [see Simple estimating of risk]
Cumulative probability graph [see Cumulative probability graph]
Simple estimating of risk - more detail [see Simple estimating of risk - more detail]
Simple estimation problems [see Simple estimation problems]
Obtaining the estimates [see Obtaining the estimates]
Breakdown of variables [see Breakdown of variables]
The Risk Management Process - Evaluate
The Risk Management Process - evaluate - estimates [see The Risk Management Process - evaluate - estimates]
The Risk Management Process - evaluate - independent correlation [see The Risk Management Process - evaluate - independent correlation]
Cumulative probability graph [see Cumulative probability graph]
The Risk Management Process - evaluate - positive correlation [see The Risk Management Process - evaluate - positive correlation]
Cumulative probability graph [see Cumulative probability graph]
The Risk Management Process - evaluate - negative correlation [see The Risk Management Process - evaluate - negative correlation]
The Risk Management Process - evaluate - conditional correlation [see The Risk Management Process - evaluate - conditional correlation]
Cumulative probability graph [see Cumulative probability graph]
Cumulative probability graph 2 [see Cumulative probability graph 2]
The Risk Management Process - Plan
Ways to modify plans [see Ways to modify plans]
The Risk Management Process - plan - plans and strategies [see The Risk Management Process - plan - plans and strategies]
Types of plans [see Types of plans]
Detailed_planning - dependencies - 4 basic types [see Detailed_planning - dependencies - 4 basic types]
Detailed_planning - dependencies - 4 basic types part 2 [see Detailed_planning - dependencies - 4 basic types part 2]
The Risk Management Process - Manage - plans and strategies [see The Risk Management Process - manage - plans and strategies]
Risk Issues
Identify risk issues [see Identify risk issues]
Other issues [see Other issues]
The contractor [see The contractor]
Other aspects [see Other aspects]
Risk combination [see Risk combination]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
Change
Progress [see Progress]
Problems of change [see Problems of change]
Freeze to freedom [see Freeze to freedom]
The three C's
The three Cs [see The three Cs]
The three Cs - action focus part 1 [see The three Cs - action focus part 1]
The three Cs - action focus part 2 [see The three Cs - action focus part 2]
Be positive
Be positive - issues and action [see Be positive - issues and action]
Be positive - be clever [see Be positive - be clever]
Be positive - when in trouble [see Be positive - when in trouble]
Be positive - project management [see Be positive - project management]
Be positive - change management [see Be positive - change management]
Be positive - communication [see Be positive - communication]
Self discipline [see Self discipline]
Be positive - change [see Be positive - change]
Be positive - attitude [see Be positive - attitude]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited
