Obviously, until a detailed plan is available covering the initial stage of the project it is very hard to estimate costs.
As part of project approval the Project Board must be presented with an overall estimate of the project costs.
The first stage plan is required in more detail for the project approval process.
Initial cost estimation will be less accurate and the extra effort involved for a more detailed costing may be too high for the majority of the project early on.
Hence, the initial cost estimate may be rather simplistic as shown below.
The summary shows the costs for a variety of resources for different periods of the project.
These can be totalled for each period to represent a simple cash flow.
Any estimation of costs should be done in liaison with the financial department for their expert input.
Estimating [see Detailed planning – part 6 - Estimating - overview]
Estimating [see Detailed planning – part 7 - Estimating - why are estimates too long?]
Estimating [see Detailed planning – part 8 - Estimating - why are estimates too short?]
Estimating [see Detailed planning – part 9 - Estimating - data usage]
Estimation [see Detailed planning – part 3 - Initial estimation - high level plan (first review)]
Estimation [see Detailed planning – part 4 - Initial estimation - high level plan (second review)]
Estimation [see Detailed planning – part 5 - Initial estimation - budget cost plan]
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
59The components [see The components]
Organization [see Organization - part 1]
Planning [see Planning (PL) - part 1]
Project Board [see Organization - part 2]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Organization [see Organization - Purpose]
Final delivery stage [see Introduction to processes - The PRINCE2 journey - Final delivery stage]
Initiation stage [see Introduction to processes - The PRINCE2 journey - Initiation stage]
Pre-project [see Introduction to processes - The PRINCE2 journey - Pre-project]
Subsequent delivery stages [see Introduction to processes - The PRINCE2 journey - Subsequent delivery stages]
Project
Appoint the Executive and the Project Manager [see Starting up a project – Activities - Appoint the Executive and the Project Manager]
Assemble the Project Initiation Documentation [see Initiating a project – Activities - Assemble the Project Initiation Documentation]
Authorize a Stage or Exception Plan [see Directing a project – Activities - Authorize a Stage or Exception Plan]
Authorize initiation [see Directing a project – Activities - Authorize initiation]
Authorize project closure [see Directing a project – Activities - Authorize project closure]
Authorize the project [see Directing a project – Activities - Authorize the project]
Capture previous lessons [see Starting up a project – Activities - Capture previous lessons]
Closing a Project - Purpose [see Closing a Project - Purpose]
Create the Project Plan [see Initiating a project – Activities - Create the Project Plan]
Design and appoint the project management team [see Starting up a project – Activities - Design and appoint the project management team]
Directing a project - Purpose [see Directing a project - Purpose]
Evaluate the project [see Closing a Project - Activities - Evaluate the project]
Give ad hoc direction [see Directing a project – Activities - Give ad hoc direction]
Hand over products [see Closing a Project - Activities - Hand over products]
Initiating a project - Purpose [see Initiating a project - Purpose]
Objective [see Closing a Project - Objective]
Objective [see Directing a project - Objective]
Objective [see Initiating a project - Objective]
Objective [see Starting up a project - Objective]
Plan the initiation stage [see Starting up a project – Activities - Plan the initiation stage]
Prepare planned closure [see Closing a Project - Activities - Prepare planned closure]
Prepare premature closure [see Closing a Project - Activities - Prepare premature closure]
Prepare the Communication Management Strategy [see Initiating a project – Activities - Prepare the Communication Management Strategy]
Prepare the Configuration Management Strategy [see Initiating a project – Activities - Prepare the Configuration Management Strategy]
Prepare the outline Business Case [see Starting up a project – Activities - Prepare the outline Business Case]
Prepare the Quality Management Strategy [see Initiating a project – Activities - Prepare the Quality Management Strategy]
Prepare the Risk Management Strategy [see Initiating a project – Activities - Prepare the Risk Management Strategy]
Recommend project closure [see Closing a Project - Activities - Recommend project closure]
Refine the Business Case [see Initiating a project – Activities - Refine the Business Case]
Select the project approach and assemble the Project Brief [see Starting up a project – Activities - Select the project approach and assemble the Project Brief]
Set up the project controls [see Initiating a project – Activities - Set up the project controls]
Starting up a project - Purpose [see Starting up a project - Purpose]
Stage
Authorize a Work Package [see Controlling a stage – Activities - Authorize a Work Package]
Capture and examine issues and risks [see Controlling a stage – Activities - Capture and examine issues and risks]
Controlling a stage - Purpose [see Controlling a stage - Purpose]
Escalate issues and risks [see Controlling a stage – Activities - Escalate issues and risks]
Managing a Stage Boundary - Purpose [see Managing a Stage Boundary - Purpose]
Objective [see Controlling a stage - Objective]
Objective [see Managing a Stage Boundary - Objective]
Plan the next stage [see Managing a Stage Boundary – Activities - Plan the next stage]
Produce an Exception Plan [see Managing a Stage Boundary – Activities - Produce an Exception Plan]
Receive completed Work Packages [see Controlling a stage – Activities - Receive completed Work Packages]
Report highlights [see Controlling a stage – Activities - Report highlights]
Report stage end [see Managing a Stage Boundary – Activities - Report stage end]
Review the stage status [see Controlling a stage – Activities - Review the stage status]
Review Work Package status [see Controlling a stage – Activities - Review Work Package status]
Take corrective action [see Controlling a stage – Activities - Take corrective action]
Update the Business Case [see Managing a Stage Boundary – Activities - Update the Business Case]
Update the Project Plan [see Managing a Stage Boundary – Activities - Update the Project Plan]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Planning
Assessment and planning [see Assessment and planning]
Implementing [see Implementing]
Prioritising [see Prioritising]
Scheduling [see Scheduling]
Review [see Review]
Introduction
What is risk? [see What is risk?]
6 questions to define the project [see 6 questions to define the project]
The key areas of concern [see The key areas of concern]
What should risk analysis provide? [see What should risk analysis provide?]
3 Ways to view risk management [see 3 Ways to view risk management]
General comments on risk assessment [see General comments on risk assessment]
Accountability [see Accountability]
General comments on planning [see General comments on planning]
What are the core process steps to assess a risk? [see What are the core process steps to assess a risk?]
Simple process outline [see Simple process outline]
What are the basic overall process steps? [see What are the basic overall process steps?]
Stakeholders [see Stakeholders]
Success measures [see Success measures]
Why carry out Risk Assessment? [see Why carry out Risk Assessment?]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited