The simple example above is for a task considered to take a total of 15 man days.
This means it would take one person 15 days to complete or 15 people one day, if it was just a matter of effort.
However, the availability of people is not always reliable.
For the above case if you have 4 people available for the job it should take 15/4 = 3.75 days to complete.
However, if they are only available for 75% of the time you only have, in effect, 4x75% = 3 people.
Thus, according to the calculation shown, the job will take 5 days.
If a task has a long elapsed time consider the possibility of breaking it down into smaller tasks as this may aid control.
Time [see Control – part 5 - Time]
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
59The components [see The components]
Planning [see Planning (PL) - part 1]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Project
Appoint the Executive and the Project Manager [see Starting up a project – Activities - Appoint the Executive and the Project Manager]
Assemble the Project Initiation Documentation [see Initiating a project – Activities - Assemble the Project Initiation Documentation]
Authorize a Stage or Exception Plan [see Directing a project – Activities - Authorize a Stage or Exception Plan]
Authorize initiation [see Directing a project – Activities - Authorize initiation]
Authorize project closure [see Directing a project – Activities - Authorize project closure]
Authorize the project [see Directing a project – Activities - Authorize the project]
Capture previous lessons [see Starting up a project – Activities - Capture previous lessons]
Closing a Project - Purpose [see Closing a Project - Purpose]
Create the Project Plan [see Initiating a project – Activities - Create the Project Plan]
Design and appoint the project management team [see Starting up a project – Activities - Design and appoint the project management team]
Directing a project - Purpose [see Directing a project - Purpose]
Evaluate the project [see Closing a Project - Activities - Evaluate the project]
Give ad hoc direction [see Directing a project – Activities - Give ad hoc direction]
Hand over products [see Closing a Project - Activities - Hand over products]
Initiating a project - Purpose [see Initiating a project - Purpose]
Objective [see Closing a Project - Objective]
Objective [see Directing a project - Objective]
Objective [see Initiating a project - Objective]
Objective [see Starting up a project - Objective]
Plan the initiation stage [see Starting up a project – Activities - Plan the initiation stage]
Prepare planned closure [see Closing a Project - Activities - Prepare planned closure]
Prepare premature closure [see Closing a Project - Activities - Prepare premature closure]
Prepare the Communication Management Strategy [see Initiating a project – Activities - Prepare the Communication Management Strategy]
Prepare the Configuration Management Strategy [see Initiating a project – Activities - Prepare the Configuration Management Strategy]
Prepare the outline Business Case [see Starting up a project – Activities - Prepare the outline Business Case]
Prepare the Quality Management Strategy [see Initiating a project – Activities - Prepare the Quality Management Strategy]
Prepare the Risk Management Strategy [see Initiating a project – Activities - Prepare the Risk Management Strategy]
Recommend project closure [see Closing a Project - Activities - Recommend project closure]
Refine the Business Case [see Initiating a project – Activities - Refine the Business Case]
Select the project approach and assemble the Project Brief [see Starting up a project – Activities - Select the project approach and assemble the Project Brief]
Set up the project controls [see Initiating a project – Activities - Set up the project controls]
Starting up a project - Purpose [see Starting up a project - Purpose]
Stage
Authorize a Work Package [see Controlling a stage – Activities - Authorize a Work Package]
Capture and examine issues and risks [see Controlling a stage – Activities - Capture and examine issues and risks]
Controlling a stage - Purpose [see Controlling a stage - Purpose]
Escalate issues and risks [see Controlling a stage – Activities - Escalate issues and risks]
Managing a Stage Boundary - Purpose [see Managing a Stage Boundary - Purpose]
Objective [see Controlling a stage - Objective]
Objective [see Managing a Stage Boundary - Objective]
Plan the next stage [see Managing a Stage Boundary – Activities - Plan the next stage]
Produce an Exception Plan [see Managing a Stage Boundary – Activities - Produce an Exception Plan]
Receive completed Work Packages [see Controlling a stage – Activities - Receive completed Work Packages]
Report highlights [see Controlling a stage – Activities - Report highlights]
Report stage end [see Managing a Stage Boundary – Activities - Report stage end]
Review the stage status [see Controlling a stage – Activities - Review the stage status]
Review Work Package status [see Controlling a stage – Activities - Review Work Package status]
Take corrective action [see Controlling a stage – Activities - Take corrective action]
Update the Business Case [see Managing a Stage Boundary – Activities - Update the Business Case]
Update the Project Plan [see Managing a Stage Boundary – Activities - Update the Project Plan]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Tasks
Projects [see Projects]
Irritating tasks [see Irritating tasks]
Combining tasks [see Combining tasks]
Planning
Assessment and planning [see Assessment and planning]
Implementing [see Implementing]
Prioritising [see Prioritising]
Scheduling [see Scheduling]
Review [see Review]
Introduction
What is risk? [see What is risk?]
6 questions to define the project [see 6 questions to define the project]
The key areas of concern [see The key areas of concern]
What should risk analysis provide? [see What should risk analysis provide?]
3 Ways to view risk management [see 3 Ways to view risk management]
General comments on risk assessment [see General comments on risk assessment]
Accountability [see Accountability]
General comments on planning [see General comments on planning]
What are the core process steps to assess a risk? [see What are the core process steps to assess a risk?]
Simple process outline [see Simple process outline]
What are the basic overall process steps? [see What are the basic overall process steps?]
Stakeholders [see Stakeholders]
Success measures [see Success measures]
Why carry out Risk Assessment? [see Why carry out Risk Assessment?]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited