Introduction
Topics
Detailed planning
It is worthwhile considering particular areas for review at intervals.
Estimating procedures is one.
How good are we at estimating?
Is it based upon personal experience, previous plans?
Should we have carried out a formal risk assessment?
If the elapsed time for a task was considered achievable did we underestimate the experience of the staff
or should we have applied more training or more man power?
Do we need to review the training policy?
When looking at training consider how it is going to be carried out:
Internal or externalCheck the cost and resource impact.
Train the trainer or the users directlyWhat is the consistency of the training, cost and resource implications?
What detail is needed?Is it user based or does it include wider business issues?
Timing of the trainingWhen should training be implemented?
What is the recruitment policy like?
It may well be that there is a complete embargo on any form of recruitment.
How long does it take to get new staff?
Who will train them?
How long will it take to get them up to speed?
Did the project have the correct quality control procedures in place and were they adhered to?
Were the objectives and the deliverables of the task clear and understood?
Were the managerial project management practices adequate to identify and review issues in good time?
Is the culture of the organization favourable to raise and react to issues at the higher level?
Has too tight a deadline been ‘set’ from on high, although all of the project team knew it to be unrealistic?
What is the morale of the staff like and what motivational factors and practices are in place to boost productivity.
All of these points could be considered.
Control
Assessing the situation [see Control – part 14 - Assessing the situation]
Contingency [see Control – part 16 - Contingency]
Controlling change – part 1 [see Control – part 18 - Controlling change – part 1]
Controlling change – part 2 [see Control – part 19 - Controlling change – part 2]
Cost - cash flow [see Control – part 9 - Cost - cash flow]
Cost - common terms [see Control – part 7 - Cost - common terms]
Cost - overspend [see Control – part 8 - Cost - overspend]
Cost [see Control – part 6 - Cost]
Document control procedures [see Control – part 20 - Document control procedures]
General [see Control – part 3 - General]
Monitoring [see Control – part 2 - Monitoring]
Progress reporting - general [see Control – part 10 - Progress reporting - general]
Progress reporting - Project Board [see Control – part 11 - Progress reporting - Project Board]
Progress reporting - what data? [see Control – part 12 - Progress reporting - what data?]
Project completion [see Control – part 21 - Project completion]
Resolving issues and problems [see Control – part 15 - Resolving issues and problems]
Taking action - what does this entail? [see Control – part 13 - Taking action - what does this entail?]
Time [see Control – part 5 - Time]
What? - scope [see Control – part 4 - What? - scope]
Why? What can go wrong? [see Control – part 1 - Why? What can go wrong?]
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
59The components [see The components]
Analysing Risks [see Planning (PL) - part 7]
Estimating [see Planning (PL) - part 5]
Organization [see Organization - part 1]
Plans - benefits [see Plans - part 1]
Quality in a Project Environment [see Quality in a Project Environment]
Risk [see Management of Risk - part 1]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Acceptance records [see Quality - The PRINCE2 approach - Quality planning - Acceptance records]
Approval records [see Quality - The PRINCE2 approach - Quality planning - Approval records]
Balancing the project, team and individual [see Organization - The PRINCE2 approach - Working with the project team - Balancing the project, team and individual]
Organization [see Organization - Purpose]
Part-time teams [see Organization - The PRINCE2 approach - Working with the project team - Part-time teams]
Product Descriptions [see Quality - The PRINCE2 approach - Quality planning - Product Descriptions]
Project Product Description [see Quality - The PRINCE2 approach - Quality planning - The Project Product Description]
Quality control [see Quality - The PRINCE2 approach - Quality control]
Quality defined [see Quality - Quality defined]
Quality methods [see Quality - The PRINCE2 approach - Quality control - Quality methods]
Quality purpose [see Quality - Purpose]
Quality records [see Quality - The PRINCE2 approach - Quality control - Quality records]
Quality Register [see Quality - The PRINCE2 approach - Quality planning - The Quality Register]
Quality The PRINCE2 approach [see Quality - The PRINCE2 approach]
The Quality Management Strategy [see Quality - The PRINCE2 approach - Quality planning - The Quality Management Strategy]
Training needs for project teams [see Organization - The PRINCE2 approach - Working with the project team - Training needs for project teams]
Plans
Activities [see Plans - The PRINCE2 approach - Identify activities and dependencies - Activities]
Analyse the risks [see Plans - The PRINCE2 approach - Analyse the risks]
Create the product breakdown structure [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Create the product breakdown structure]
Create the product flow diagram [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Create the product flow diagram]
Dependencies [see Plans - The PRINCE2 approach - Identify activities and dependencies - Dependencies]
Design the plan - Write the Project Product Description [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Write the Project Product Description]
Document the plan [see Plans - The PRINCE2 approach - Document the plan]
Exception Plans [see Plans - Plans defined - Exception Plans]
Levels of plan [see Plans - Plans defined - Levels of plan]
Plans - Define and analyse the products [see Plans - The PRINCE2 approach - Define and analyse the products]
Plans - Philosophy [see Plans - The PRINCE2 approach - Philosophy]
Plans - Purpose [see Plans - Purpose]
Prepare estimates [see Plans - The PRINCE2 approach - Prepare estimates]
Prepare the schedule - Agree control points [see Plans - The PRINCE2 approach - Prepare the schedule - Agree control points]
Prepare the schedule - Assess resource availability [see Plans - The PRINCE2 approach - Prepare the schedule - Assess resource availability]
Prepare the schedule - Assign resources [see Plans - The PRINCE2 approach - Prepare the schedule - Assign resources]
Prepare the schedule - Calculate total resource requirements and costs [see Plans - The PRINCE2 approach - Prepare the schedule - Calculate total resource requirements and costs]
Prepare the schedule - Define activity sequence [see Plans - The PRINCE2 approach - Prepare the schedule - Define activity sequence]
Prepare the schedule - Define milestones [see Plans - The PRINCE2 approach - Prepare the schedule - Define milestones]
Prepare the schedule - Level resource usage [see Plans - The PRINCE2 approach - Prepare the schedule - Level resource usage]
Prepare the schedule [see Plans - The PRINCE2 approach - Prepare the schedule]
Prerequisites for planning – design the plan [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan]
Project Plan [see Plans - Plans defined - The Project Plan]
Stage Plans [see Plans - Plans defined - Stage Plans]
Team Plans [see Plans - Plans defined - Team Plans]
What is a plan? [see Plans - Plans defined - What is a plan?]
What is planning? [see Plans - Plans defined - What is planning?]
Write the Product Descriptions [see Plans - The PRINCE2 approach - Prerequisites for planning – design the plan - Write the Product Descriptions]
Risk
Assess [see Risk - Risk management procedure - Assess]
Communicate [see Risk - Risk management procedure - Communicate]
Identify – part 1 [see Risk - Risk management procedure - Identify – part 1]
Implement [see Risk - Risk management procedure - Implement]
Plan [see Risk - Risk management procedure - Plan]
Risk management in projects [see Risk - Risk management in projects]
Risk management procedure [see Risk - Risk management procedure]
Risk Management Strategy [see Risk - Risk Management Strategy]
Risk Register [see Risk - Risk Register]
What is a risk? [see Risk - Risk defined - What is a risk?]
What is at risk? [see Risk - Risk defined - What is at risk?]
What is risk management? [see Risk - Risk defined - What is risk management?]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Introduction
What is risk? [see What is risk?]
6 questions to define the project [see 6 questions to define the project]
The key areas of concern [see The key areas of concern]
What should risk analysis provide? [see What should risk analysis provide?]
3 Ways to view risk management [see 3 Ways to view risk management]
General comments on risk assessment [see General comments on risk assessment]
Accountability [see Accountability]
General comments on planning [see General comments on planning]
What are the core process steps to assess a risk? [see What are the core process steps to assess a risk?]
Simple process outline [see Simple process outline]
What are the basic overall process steps? [see What are the basic overall process steps?]
Stakeholders [see Stakeholders]
Success measures [see Success measures]
Why carry out Risk Assessment? [see Why carry out Risk Assessment?]
Assessment of risks
Common methods of assessing risk [see Common methods of assessing risk]
Common methods of assessing risk 2 [see Common methods of assessing risk 2]
Issue based [see Issue based]
Checklists [see Checklists]
Qualitative method [see Qualitative method]
Quantitative method [see Quantitative method]
Quantitative method part 2 [see Quantitative method part 2]
Quantitative method part 3 [see Quantitative method part 3]
Quantitative method part 4 [see Quantitative method part 4]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
The emerging leader
Emerging leaders [see Emerging leaders]
The boss [see The boss]
Training
Training [see Training]
Training selection [see Training selection]
Training opportunity [see Training opportunity]
Follow the leader [see Follow the leader]
Follow the leader - adverse behaviour [see Follow the leader - adverse behaviour]
Chess the middle game [see Chess the middle game]
Standards [see Standards]
At the top
Letting go [see Letting go]
Continuity [see Continuity]
Top of the ladder [see Top of the ladder]
Loneliness at the top part 1 [see Loneliness at the top part 1]
Loneliness at the top part 2 [see Loneliness at the top part 2]
The Top team [see The Top team]
Motivation
Motivation [see Motivation]
Motivation Douglas McGregors X and Y theory [see Motivation Douglas McGregors X and Y theory]
Motivation - Abraham Maslow [see Motivation - Abraham Maslow]
Motivation - Frederick Herzberg [see Motivation - Frederick Herzberg]
Motivation - key problems [see Motivation - key problems]
Motivation - people part 1 [see Motivation - people part 1]
Motivation - people part 2 [see Motivation - people part 2]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited
