Introduction
Topics
Detailed planning
Your project will only be successful if the customer wants the product.
Obviously, at the start of a project there is a customer that wants a particular product.
It is up to the Project Manager via the management team to ascertain the exact nature of the product.
That is, the user expectations.
The user expectations in the form of the product specification should be clear, unambiguous and agreed by all stakeholders.
Remember, this will include performance criteria and field testing prior to delivery.
It may also include support for the product for some months after delivery.
This is common in the construction industry with contractor payments being held back to encourage completion.
It will be up to the project management team to challenge what the customer really wants.
Never assume what the customer wants.
When a project ends the customer gets their product.
It may well have been produced to the exact specifications but is it what the customer was expecting.
It should be if there has been good communication with the customer during the generation of the specifications.
Such a situation must be avoided at all costs.
Clarify, clarify and then clarify again.
You will need to build in control measures to make sure you are still on track and that the customer has not changed his mind.
To avoid misconstruing the customer needs review the requirements regularly.
Construction [see Construction projects – part 1]
Project manager [see Project manager – part 1 - Overview]
Project manager [see Project manager – part 2 - Choosing the project team]
Project manager [see Project manager – part 3 - People recruitment]
Project manager [see Project manager – part 4 - Communication]
Project manager [see Project manager – part 6 - Systematic approach]
Project manager [see Project manager – part 7 - Empowerment]
Project manager [see Project manager – part 8 - Appointment]
Introduction
Definition [see Introduction part 1]
Terminology [see Introduction part 2]
What is a project? Scope [see Introduction part 3]
The processes [see Introduction part 4]
Introduction to processes [see Introduction to processes]
59The components [see The components]
Appointing an Executive and Project Manager [see Starting up a Project (SU) - part 2]
Designing a Project Management Team [see Starting up a Project (SU) - part 3]
Introduction
Foreword [see Foreword]
Purpose [see Introduction part 1]
What does a project manager do? [see Introduction part 2a]
What is it we wish to control? [see Introduction part 2b]
The structure of PRINCE2 [see Introduction part 2c]
What PRINCE2 does not provide [see Introduction part 3]
Dealing with changes to the project management team [see Organization - The PRINCE2 approach - The project management team – Dealing with changes to the project management team]
Project Manager [see Organization - The PRINCE2 approach - The project management team - Project Manager]
Project Board [see Organization - The PRINCE2 approach - The project management team - Project Board]
Project management team structure [see Organization - The PRINCE2 approach - The project management team]
Size of the Project Board [see Organization - The PRINCE2 approach - The project management team - Size of the Project Board]
Stakeholder engagement [see Organization - The PRINCE2 approach - Working with stakeholders- Stakeholder engagement]
Stakeholders [see Principles - Defined roles and responsibilities]
The Communication Management Strategy [see Organization - The PRINCE2 approach - Working with stakeholders - The Communication Management Strategy]
Types of stakeholder [see Organization - The PRINCE2 approach - Working with stakeholders- Types of stakeholder]
Change
Capture [see Change - The PRINCE2 approach - Issue and change control procedure - Capture]
Configuration Item Records [see Change - The PRINCE2 approach - Establish controls - Configuration Item Records]
Configuration management [see Change - Change defined - Configuration management]
Configuration management procedure [see Change - The PRINCE2 approach - Configuration management procedure]
Configuration Management Strategy [see Change - The PRINCE2 approach - Establish controls - Configuration Management Strategy]
Daily Log [see Change - The PRINCE2 approach - Establish controls - Daily Log]
Decide [see Change - The PRINCE2 approach - Issue and change control procedure - Decide]
Establish controls [see Change - The PRINCE2 approach - Establish controls]
Examine [see Change - The PRINCE2 approach - Issue and change control procedure - Examine]
Implement [see Change - The PRINCE2 approach - Issue and change control procedure - Implement]
Issue and change control [see Change - Change defined - Issue and change control]
Issue and change control procedure [see Change - The PRINCE2 approach - Issue and change control procedure]
Issue Register [see Change - The PRINCE2 approach - Establish controls - Issue Register]
Issue Report [see Change - The PRINCE2 approach - Establish controls - Issue Report]
Issues [see Change - Change defined - Issues]
Product Status Account [see Change - The PRINCE2 approach - Establish controls - Product Status Account]
Propose [see Change - The PRINCE2 approach - Issue and change control procedure - Propose]
Types of issue [see Change - Change defined - Types of issue]
Project
Appoint the Executive and the Project Manager [see Starting up a project – Activities - Appoint the Executive and the Project Manager]
Assemble the Project Initiation Documentation [see Initiating a project – Activities - Assemble the Project Initiation Documentation]
Authorize a Stage or Exception Plan [see Directing a project – Activities - Authorize a Stage or Exception Plan]
Authorize initiation [see Directing a project – Activities - Authorize initiation]
Authorize project closure [see Directing a project – Activities - Authorize project closure]
Authorize the project [see Directing a project – Activities - Authorize the project]
Capture previous lessons [see Starting up a project – Activities - Capture previous lessons]
Closing a Project - Purpose [see Closing a Project - Purpose]
Create the Project Plan [see Initiating a project – Activities - Create the Project Plan]
Design and appoint the project management team [see Starting up a project – Activities - Design and appoint the project management team]
Directing a project - Purpose [see Directing a project - Purpose]
Evaluate the project [see Closing a Project - Activities - Evaluate the project]
Give ad hoc direction [see Directing a project – Activities - Give ad hoc direction]
Hand over products [see Closing a Project - Activities - Hand over products]
Initiating a project - Purpose [see Initiating a project - Purpose]
Objective [see Closing a Project - Objective]
Objective [see Directing a project - Objective]
Objective [see Initiating a project - Objective]
Objective [see Starting up a project - Objective]
Plan the initiation stage [see Starting up a project – Activities - Plan the initiation stage]
Prepare planned closure [see Closing a Project - Activities - Prepare planned closure]
Prepare premature closure [see Closing a Project - Activities - Prepare premature closure]
Prepare the Communication Management Strategy [see Initiating a project – Activities - Prepare the Communication Management Strategy]
Prepare the Configuration Management Strategy [see Initiating a project – Activities - Prepare the Configuration Management Strategy]
Prepare the outline Business Case [see Starting up a project – Activities - Prepare the outline Business Case]
Prepare the Quality Management Strategy [see Initiating a project – Activities - Prepare the Quality Management Strategy]
Prepare the Risk Management Strategy [see Initiating a project – Activities - Prepare the Risk Management Strategy]
Recommend project closure [see Closing a Project - Activities - Recommend project closure]
Refine the Business Case [see Initiating a project – Activities - Refine the Business Case]
Select the project approach and assemble the Project Brief [see Starting up a project – Activities - Select the project approach and assemble the Project Brief]
Set up the project controls [see Initiating a project – Activities - Set up the project controls]
Starting up a project - Purpose [see Starting up a project - Purpose]
Introduction
Resources [see Resources]
Workaholic [see Workaholic]
What is time management? [see What is time management? Problem Time solving]
What is time management? [see What is time management? General]
Key time destroyers
Key Time Destroyers [see Key Time Destroyers]
Action chasing [see Action chasing]
Being disorganised [see Being disorganised]
Cant say 'No' [see Cant say 'No']
Crisis management [see Crisis management]
Desktop management [see Desktop management]
Friends [see Friends]
Large reports [see Large reports]
Low energy levels [see Low energy levels]
Meetings 1 [see Meetings 1]
Meetings 2 [see Meetings 2]
Multiple tasks [see Multiple tasks]
Others errors [see Others errors]
Other's jobs [see Other's jobs]
Paperwork [see Paperwork]
Perfection [see Perfection]
Poor communication [see Poor communication]
Poor control and reporting [see Poor control and reporting]
Poor delegation [see Poor delegation]
Poor information [see Poor information]
Poor leadership [see Poor leadership]
Poor planning [see Poor planning]
Poor preparation [see Poor preparation]
Poor self discipline [see Poor self discipline]
Putting things off [see Putting things off]
Resource issues [see Resource issues]
Responsibility, accountability and authority [see Responsibility, accountability and authority]
Socialising [see Socialising]
Staff issues [see Staff issues]
The boss [see The boss]
The telephone 1 [see The telephone 1]
The telephone 2 [see The telephone 2]
Travel time [see Travel time]
Unfinished tasks [see Unfinished tasks]
Unwanted callers [see Unwanted callers]
Work overload [see Work overload]
Your own errors [see Your own errors]
Introduction
What is risk? [see What is risk?]
6 questions to define the project [see 6 questions to define the project]
The key areas of concern [see The key areas of concern]
What should risk analysis provide? [see What should risk analysis provide?]
3 Ways to view risk management [see 3 Ways to view risk management]
General comments on risk assessment [see General comments on risk assessment]
Accountability [see Accountability]
General comments on planning [see General comments on planning]
What are the core process steps to assess a risk? [see What are the core process steps to assess a risk?]
Simple process outline [see Simple process outline]
What are the basic overall process steps? [see What are the basic overall process steps?]
Stakeholders [see Stakeholders]
Success measures [see Success measures]
Why carry out Risk Assessment? [see Why carry out Risk Assessment?]
Introduction
Definition of leadership [see Definition of leadership]
Leadership and effectiveness [see Leadership and effectiveness]
Leadership qualities [see Leadership qualities]
Leadership functions [see Leadership functions]
The vision
Practicality [see Practicality]
Stakeholders [see Stakeholders]
The vision [see The vision]
The vision - preparing [see The vision - preparing]
The vision - personalities [see The vision - personalities]
The vision - general [see The vision - general]
Communication
Open questions [see Open questions]
Meetings [see Meetings]
Agenda [see Agenda]
other sites of interest in the series
© Copyright 2011 all rights reserved March Limited
