Risk management - How do we carry out the simulations?

How do we carry out the simulations?

We have already mentioned that in order to assess risk we need to carry out a number of simulations.
In order to do this for each activity we will have proposed a MINIMUM, LIKELY and MAXIMUM value and we could have any number of activities.

For each of these activities we need to generate a random value and add them up to give a project total (for cost or durations).

The only was to do this, and retain some sanity, is to use a suitable piece of software that will generate the random numbers for us and carry out the necessary calculations.

Such software can be used within spreadsheet programmes such as Lotus 1-2-3 and Excel.
A simple programme to use is @RISK.
More information can be found on this programme by searching for @RISK in Google.
This training package will not go into the details of using risk management software.